Main Contractor
Chester Ceilings Limited
Location
Sighthill, Edinburgh
Date
Sep 19 – June 20
Services
On this project we worked closely with the main contractor over a three week period. We erected the jumbo stud partition wall and suspended ceiling system at a retail unit in Edinburgh.
The works included the erection of a double 146mm Gypframe jumbo stud wall back to back, incorporating a third stud which provided additional stability while tying the two walls together.
We then applied two layers of 12.5mm fireline plasterboard to either side. Our operatives were working at heights of up to 10m during this project.